Road works are to be carried out at Station Road (B4060) in Yate from 1st-26th June. These will involve upgrading an existing pedestrian crossing, widening Station Road (to accommodate three lanes on the approach to Morrison’s roundabout), amending an existing island and carrying out three utility connections. The road will then be resurfaced. The work will be done in three phases:
Phase 1. 1st June – 13th June. Civils work. Morrison’s Roundabout to JunctionThe Glen. Access to all roads and car parks will be available at all times via Link Road.
Phase 2. 14th June – 20th June. Carriageway Resurfacing. Morrison Roundabout to Church Road Junction.
Phase 3. 21st June – 26th June. Carriageway Resurfacing. Church Road Junction to Link Road Roundabout.
The road will be subject to a closure for the duration of the works and a diversion route (Kennedy Way – Link Road) for traffic will be set up. Access to properties fronting the site will be available for the majority of this closure. However there will unfortunately have to be short periods of time when they will have to resurface across junctions which will restrict access. Every effort will be made to keep disruption to local residents to a minimum for the duration of the works. The dates may change due to bad weather or problems with equipment.
No comments:
Post a Comment