People living close to the road bridge on Church Road have been given more details on the upcoming works to replace it.
Initial work to
construct a temporary pedestrian bridge downstream of the existing
bridge will begin on 17 March and Church Road will remain open during
this time.
From
7 April, Church Road will close for three weeks while preliminary works
are carried out on the existing bridge. Diversions will be in place
during this time. Church Road will reopen after this phase.
From 28 July, Church Road will close
for six weeks to allow for demolition of the existing bridge and
construction of the new bridge. The work has been scheduled to take
place during the school summer holidays to minimise disruption to school
bus service. Diversions will be in place during this time.
Further information on this and other
major road schemes taking place in South Gloucestershire between now and
March 2015 are available at www.southglos.gov.uk/nfringeworks