From 20th March for 11 weeks there will be night time southbound closures of the M32 to enable the central reservation barrier over the Eastville Viaduct to be replaced.
To try to minimise disruption, the contractors will carry out the work between 8pm and 6am Monday to Friday, so the M32 will remain open in both directions during the day. At night the southband carriageway will be completely closed. There may also be times when they need to close a section of the northbound carriageway too, but these times are not yet finalised. They will be liasing with contractors on other nearby projects, such as MetroBus.
Unfortunately they won't be able to lift the 40mph restrictions when this work is complete because futher work needs to be carried out on the viaduct parapets.
If you have any queries or comments about the works and would like further information, please contact the Highways England Customer Contact Centre on 0300 123 5000 or by email: info@highwaysengland.co.uk.