Thursday, 20 July 2017

Yate Spur cycle route progress (and delays)

There's good news and bad news about the long-awaited cycle track between Yate and the Railway Path, the cycling "superhighway" between Bristol and Bath. At the moment the Yate Spur only comes out as far as the T junction on Westerleigh Road south of Westerleigh.

  • Westerleigh Road T junction to Broad Lane (Cornerways) - inside the farmer's field up to the former Cornerways Nursery - Construction starts this month, taking 4 months 
  • Broad Lane - has already been upgraded 
  • Broad Lane to Nibley Lane Corner - the "Westerleigh bypass" - being designed, awaiting funding 
  • Nibley Lane Corner improvements - recently consulted about - on hold until Spring 2018 because of expected heavy traffic during the Bromley Heath Viaduct work 
  • Section under railway viaduct to Westerleigh Rd mini-roundabout - being designed, awaiting funding 
  • Westerleigh Rd mini-roundabout to Yate Common - on hold until January 2018 because of railway embankment work near Chedworth
Once the section from Westerleigh Road to Cornerways is done, there will be a continuous link from the Railway Path to opposite Wot Not at the north end of Westerleigh. We are pressing for any outstanding maintenance to be carried out between Broad Lane and Wot Not - it tends to get overgrown from time to time.

No comments: