Tuesday, 2 May 2017

Update on M32 Eastville viaduct works

Since starting work at the end of March, contractors have been making good progress with the removal of the central reservation barrier at the Eastville Viaduct on the M32. Over the last two weeks they have been removing the worn-out barrier.

They are now working to remove covers and install steel plates to 49 manholes and inspection chambers to provide a flat surface on which the new concrete central barrier can be placed.

They now moving into a new phase of work, with the overnight traffic management changing from the beginning of May. Instead of being closed between Junctions 2 (Fishponds) and 3 (Bristol City Centre), the M32 will be closed southbound from Junction 1 (Hambrook) and Junction 3 (Bristol City Centre). A fully signed diversion taking traffic via the A4174, A38 Gloucester Road and the A4044 Bond Street will be in place instead.

The closures mostly affect the southbound carriageway, but there may be times where they need to close the northbound carriageway too.

To keep updated with the closures of the M32, please visit www.trafficengland.com. You can also follow @HighwaySWEST on Twitter for updates.

If you have any concerns or issues regarding these works you can contact the Highways England Customer Contact Centre on 0300 123 5000.

Friday, 28 August 2015

Westerleigh Road closure

Westerleigh Road will be closed temporarily from its junction with Besom Lane north for 150m to enable signing works to go ahead. The closure order starts on 6 September for a maximum period of 18 months but it won't be closed for the whole period - the work is only expected to take one day.

Tuesday, 15 July 2014

Work on Nibley substation planned for October

Last year Claire Young got in contact with Western Power after residents raised concerns about a new substation that had been installed on an area of open grass at Nibley. The wrong size box had been used and it was installed the wrong way round, so it overhung its concrete base.

Claire recently got in touch with the company again to find out why the problems still hadn't been corrected and to ask about a pole that is leaning over. Western Power say that the work to connect the new substation to the high voltage network will start on October 23rd 2014 and will involve traffic lights and the closure of Nibley Lane (the Badminton Road to Iron Acton stretch).

The existing building will be changed to one the correct size for the plinth and the poles changed and the old ones removed at the same time. Western Power assure residents that the old pole is not a danger, it had been identified as needing changing in the next 10 years so they will do it at the same time as the rest of the work.

The delay has been because they have been inundated with customer requests for new connections, cable diversions and generator connections, which take priority over internal works.

Tuesday, 17 June 2014

One day closure for Nibley Road

Nibley Lane between Badminton Road and Westerleigh Road is expected to close on Friday 20th June for drainage works to be carried out.

Tuesday, 5 February 2013

Nibley Lane to close for cleaning Friday

Nibley Lane is expected to close for cleaning from its junction with Badminton Road to its junction with Westerleigh Road on Friday 8th February 2013 from 9.30am until 2.30pm.

Monday, 8 March 2010

Roadwork round-up

  • There will be traffic lights on Westerleigh Road near the Cooks Lane junction from 9-11 March so the road can be repaired.
  • The B4058 Wotton Road will be closed from B4059 Iron Acton Way to Manor Road between 15-28 March to enable the road to be resurfaced.
  • The B4058 Wotton Road, from Charfield Road B4059 eastwards for 500 metres (near the Post Office) will have temporary traffic lights and width restrictions 22 March - 6 April for resurfacing work to take place.